We are pleased to provide an update on the second weighbridge installation at Armidale Waste Management Facility (Long Swamp Road), aimed at improving the overall experience for all users. The addition of the second weighbridge will bring significant benefits, including:
Project timeline and progress photos of the weighbridge installation.
16 September 2024- onsite work commenced on
3 March 2025- the concrete slab has been poured and is curing, ready for the delivery of the weighbridge this week.
6 March 2025– weighbridge beams delivered and installed on site
28 March 2025– weighbridge deck poured and will cure for 28 days before the electrical components are installed
Impact on users
While these improvements will greatly enhance the facility, we kindly ask for your patience as there may be short delays when entering or leaving the facility. Please drive slowly and follow any instructions from Waste Facility staff to ensure the safety and smooth operation of the site.
We appreciate your cooperation as we work to improve the facility for all users.