Wirruna Street water main upgrade

  • Project typeWater
  • Project schedule6 weeks weather permitting
  • Contractor nameCouncil in-house construction crews

Project Purpose:
To replace the existing ageing water main, which has reached the end of its service life and has experienced multiple bursts, leaks and water flow issues.

Scope of Works:

  • Install a new 100mm PVC water main along the northern side of Wirruna Street.
  • Install a new 63mm poly pipeline along sections of the southern side.
  • Replace existing property water connections with new copper service lines.
  • Connect the new pipelines to the town water network.
  • Remove dead ends from the network to improve water reticulation and water quality.
  • Relocate the water main to footpath areas to make future maintenance easier.

Benefits:

  • Improved reliability of the local water supply.
  • Enhanced water reticulation and water quality.
  • Reduced risk of future water main failures, bursts and leaks.
  • Easier maintenance and access for future repairs.
  • Continued safe and dependable water supply for residents.

Potential Impacts During Construction:

  • Temporary water interruptions.
  • Short periods of restricted driveway access.
  • Construction noise.
  • Temporary footpath closures.

Location

Wirruna Street, Guyra, Suburb 2 2365  View Map

Google Map