Guyra Water Treatment Facility 2026 Projects & Maintenance

Guyra Water Treatment Facility Projects and Maintenance for 2026

Guyra Bottom Dam – Destratification

  • Current Status: REF and design completed; awaiting Safety in Design workshop.
  • Jan 2026: Safety in Design workshop.
  • Early 2026: Department of Climate Change, Energy, the Environment and Water (DCCEEW) review.
  • Q1 FY 2026–2027: Tender process.
  • Q2 FY 2026–2027: Installation and commissioning.

 

Powder Activated Carbon (PAC) Dosing Unit

  • Current Status: Construction underway.
  • Until BGA Season Ends: Cannot take process offline.
  • By June 2026: Delivery, installation, and commissioning.

 

Automation at Guyra WTP

  • Jan 2026: Begin basic automation design and electrical switchboard upgrade design.
  • Ongoing: Electrical upgrades and automation improvements.

Q3 FY 2026–2027: Install new electrical switchboard (critical for high-level automation and safety).